Delivery Update – January 2023

January 2023 was a busy month following a short pause in works over the festive period.


Some of our key achievements during January included:

  • excavation of tunnel boring receival pit on Fourteenth Avenue, Austral for the Kemps Creek Carrier

  • preparations for the pressure main on Gurner Avenue including a wastewater pipeline between new pump station and existing pump station

  • excavation of maintenance hole on Fourteen Avenue, Austral

  • completed 60 percent of main works for Kemps Creek Carrier

  • completed 95 percent of main works for Bonds Creek Carrier

  • began installing new wastewater pipes for the Bonds Creek Carrier Lead-in


Looking forward into February, weather and ground conditions permitting, we will be focused on:

  • starting excavation and preparation work to install piping and maintenance holes along Fourteenth Avenue, Austral

  • continued tunnel boring along Gurner Avenue, with a view to completing these works by March 2023

  • continued pipe and maintenance hole installation for the Austral Creek Carrier and Lead-in

See below images captured by our delivery team of their progress throughout January. Don’t forget to come back again next month for our February 2023 delivery update.

Image 1: Maintenance hole installation along Fourteenth Avenue, Austral


Image 2: Excavation of tunnel boring receival pit for Kemps Creek Carrier on Fourteenth Avenue, Austral


Image 3: Preparations for pressure main on Gurner Avenue, Austral


Image 4: Excavation of maintenance hole on Fourteenth Avenue, Austral (side view)


Image 5: Excavation of maintenance hole on Fourteenth Avenue, Austral (ariel view)