Delivery Update – January 2023
January 2023 was a busy month following a short pause in works over the festive period.
Some of our key achievements during January included:
excavation of tunnel boring receival pit on Fourteenth Avenue, Austral for the Kemps Creek Carrier
preparations for the pressure main on Gurner Avenue – including a wastewater pipeline between new pump station and existing pump station
excavation of maintenance hole on Fourteen Avenue, Austral
completed 60 percent of main works for Kemps Creek Carrier
completed 95 percent of main works for Bonds Creek Carrier
began installing new wastewater pipes for the Bonds Creek Carrier Lead-in
Looking forward into February, weather and ground conditions permitting, we will be focused on:
starting excavation and preparation work to install piping and maintenance holes along Fourteenth Avenue, Austral
continued tunnel boring along Gurner Avenue, with a view to completing these works by March 2023
continued pipe and maintenance hole installation for the Austral Creek Carrier and Lead-in
See below images captured by our delivery team of their progress throughout January. Don’t forget to come back again next month for our February 2023 delivery update.
Image 1: Maintenance hole installation along Fourteenth Avenue, Austral
Image 2: Excavation of tunnel boring receival pit for Kemps Creek Carrier on Fourteenth Avenue, Austral
Image 3: Preparations for pressure main on Gurner Avenue, Austral
Image 4: Excavation of maintenance hole on Fourteenth Avenue, Austral (side view)
Image 5: Excavation of maintenance hole on Fourteenth Avenue, Austral (ariel view)