Delivery Update - August 2023

Servicing remains on track for December 2023, following another productive month in delivering the Austral Leppington Wastewater Stage 3, Phase 1 project. Some of our key achievements for the month include:

  • completed all wastewater pipe installation along the Austral Carrier and lead-ins
  • completed maintenance hole installation on Bonds Creek carrier and Bonds Creek carrier lead-in
  • completed power connection along Gurner Avenue for proposed pumping station
  • ongoing works at the pumping station on Gurner Avenue including installation of piping and services

Looking forward into September, weather and ground conditions permitting, we will focus on:

  • completing final installation of maintenance holes along Gurner Avenue
  • ongoing installation of pump station electrical switch room at Gurner Avenue
  • completing maintenance hole installation for the Austral carrier and Kemps Creek carrier
  • commence the installation of vent shafts on Kemps Creek carrier, Bonds Creek carrier, Austral carrier and Bonds Creek carrier lead-in

See below images captured by our delivery team of their progress throughout August. The July-September 2023 quarterly update will be posted on this page during early October 2023.

Image 1: Maintenance hole installation along Thirteenth Avenue, Austral

Image 2: Sewer maintenance hole installation on Bonds Creek carrier and Bonds Creek carrier lead-in

Image 3 : Assembly and installation of piping at the pumping station on Gurner Avenue, Austral

Image 4: Gurner Avenue pumping station, construction in progress