Delivery Update - August 2023
Servicing remains on track for December 2023, following another productive month in delivering the Austral Leppington Wastewater Stage 3, Phase 1 project. Some of our key achievements for the month include:
- completed all wastewater pipe installation along the Austral Carrier and lead-ins
- completed maintenance hole installation on Bonds Creek carrier and Bonds Creek carrier lead-in
- completed power connection along Gurner Avenue for proposed pumping station
- ongoing works at the pumping station on Gurner Avenue including installation of piping and services
Looking forward into September, weather and ground conditions permitting, we will focus on:
- completing final installation of maintenance holes along Gurner Avenue
- ongoing installation of pump station electrical switch room at Gurner Avenue
- completing maintenance hole installation for the Austral carrier and Kemps Creek carrier
- commence the installation of vent shafts on Kemps Creek carrier, Bonds Creek carrier, Austral carrier and Bonds Creek carrier lead-in
See below images captured by our delivery team of their progress throughout August. The July-September 2023 quarterly update will be posted on this page during early October 2023.
Image 1: Maintenance hole installation along Thirteenth Avenue, Austral
Image 2: Sewer maintenance hole installation on Bonds Creek carrier and Bonds Creek carrier lead-in
Image 3 : Assembly and installation of piping at the pumping station on Gurner Avenue, Austral
Image 4: Gurner Avenue pumping station, construction in progress