Delivery Update - July 2023
July was a productive month for the Austral Leppington Wastewater Stage 3, Phase 1 project. With good progress being made, we remain on track for servicing in December 2023. Some of our key achievements during July include:
- completed all wastewater pipe tunnelling for the Austral carrier, Bonds Creek carrier, and Bonds Creek carrier lead-in
- nearing completion of wastewater pipe tunnelling for the Austral carrier lead-in
- ongoing delivery, excavation, and installation of maintenance holes – Austral carrier, Bonds Creek carrier, Kemps Creek carrier, Austral lead-in and Bonds Creek carrier lead-in
- installed wet well, valve chamber, electrical, water and power services to the new pumping station on Gurner Avenue
Looking forward into August, weather and ground conditions permitting, we will be focused on:
- completing wastewater pipe tunnelling for the Austral carrier lead-in
- completing the installation and testing of critical maintenance holes for the Bonds Creek Carrier and Bonds Creek Carrier lead-in
- continued installation and testing of maintenance holes for the Austral carrier, Bonds Creek carrier, and Bonds Creek Carrier lead-in with a view to have these completed by the end of August
See below images captured by our delivery team of their progress throughout July.
The August 2023 monthly update will be posted on this page during early September 2023.
Image 1: Shaft excavation in preparation of maintenance hole installation on Thirteenth Avenue
Image 2: Installation of upper section of maintenance hole in the shaft along Gurner Avenue
Image 3: Turning the maintenance hole from horizontal to vertical before installation along Gurner Avenue
Image 4: Breakthrough of the tunnel boring machine at Fourteenth Avenue, Austral
Image 5: Installation of precast pump station at Gurner Avenue Austral