Delivery Update - May 2023
With no significant delays due to wet weather experienced during May, completion of the Austral Leppington Wastewater Stage 3, Phase 1 project remains on track for December 2023. Some of our key achievements for the project during May include:
- Ongoing tunnelling of wastewater pipes - Kemps Creek carrier, Austral carrier and the Bonds Creek Carrier
- Ongoing delivery, excavation and installation of critical maintenance holes
- Ongoing concreting at the Gurner Avenue pumping station
Looking forward into June, weather and ground conditions permitting, we will be focused on:
- Completing the tunnelling of the Kemps Creek and Bonds Creek carriers and lead-ins
- Ongoing installation and testing of critical maintenance holes
- Completing concreting at the Gurner Avenue pumping station and testing it before installation of the internal pumps & pipework
See below images captured by our delivery team of their progress throughout May.
The April-June 2023 quarterly update will be posted on this page during early July 2023.
Image 2: Installation of upper section of maintenance hole along Fourteenth Avenue
Image 3: Delivery of maintenance hole at Thirteenth Avenue
Image 4: Precast concrete wet well for the new pump station at Gurner Ave