Delivery Update - May 2023

With no significant delays due to wet weather experienced during May, completion of the Austral Leppington Wastewater Stage 3, Phase 1 project remains on track for December 2023. Some of our key achievements for the project during May include:

  • Ongoing tunnelling of wastewater pipes - Kemps Creek carrier, Austral carrier and the Bonds Creek Carrier
  • Ongoing delivery, excavation and installation of critical maintenance holes
  • Ongoing concreting at the Gurner Avenue pumping station

Looking forward into June, weather and ground conditions permitting, we will be focused on:

  • Completing the tunnelling of the Kemps Creek and Bonds Creek carriers and lead-ins
  • Ongoing installation and testing of critical maintenance holes
  • Completing concreting at the Gurner Avenue pumping station and testing it before installation of the internal pumps & pipework

See below images captured by our delivery team of their progress throughout May.

The April-June 2023 quarterly update will be posted on this page during early July 2023.

Image 1: Installation of maintenance hole 3 on Thirteenth Avenue


Image 2: Installation of upper section of maintenance hole along Fourteenth Avenue


Image 3: Delivery of maintenance hole at Thirteenth Avenue


Image 4: Precast concrete wet well for the new pump station at Gurner Ave