Our Projects in Bayside Council

Share Our Projects in Bayside Council on Facebook Share Our Projects in Bayside Council on Twitter Share Our Projects in Bayside Council on Linkedin Email Our Projects in Bayside Council link

We have active project across the LGA, click on your suburb below to find out more.

Arncliffe, Banksia, Bardwell Park, Bardwell Valley, Bexley, Bexley North, Botany, Brighton-Le-Sands, Carlton (part), Daceyville, Eastgardens, Eastlakes, Hillsdale, Kingsgrove (part), Kogarah (part), Mascot, Rockdale, Rosebery (part), Turrella and Wolli Creek.

For more information

We’re here to help! You can always contact us during normal business hours on Delivering4Customers@sydneywater.com.au or 1800 006 113 and select option 2. If we are unable to answer, or if you are calling outside normal business hours, leave a detailed message and we'll get back to you as soon as possible or the next business day.

We have active project across the LGA, click on your suburb below to find out more.

Arncliffe, Banksia, Bardwell Park, Bardwell Valley, Bexley, Bexley North, Botany, Brighton-Le-Sands, Carlton (part), Daceyville, Eastgardens, Eastlakes, Hillsdale, Kingsgrove (part), Kogarah (part), Mascot, Rockdale, Rosebery (part), Turrella and Wolli Creek.

For more information

We’re here to help! You can always contact us during normal business hours on Delivering4Customers@sydneywater.com.au or 1800 006 113 and select option 2. If we are unable to answer, or if you are calling outside normal business hours, leave a detailed message and we'll get back to you as soon as possible or the next business day.

  • Arncliffe 2205

    Share Arncliffe 2205 on Facebook Share Arncliffe 2205 on Twitter Share Arncliffe 2205 on Linkedin Email Arncliffe 2205 link

    Northern Georges River Submain - Wastewater Upgrade

    Project timing: May 2024 to August 2025

    We’re upgrading 3 km section of a large wastewater main knows as the Northern Georges River Submain. This system services the community from Fairfield to Arncliffe. Our work will increase the capacity within the tunnel, improving its function and reliability of your wastewater service.

    Most of our work is underground, however we will have four major sites set up above ground for access into the wastewater system and desilting activities.

    Work involves:

    Site establishment and traffic management

    • four major sites and four minor sites will be set up in suburbs Arncliffe, Rockdale and Kogarah

    Desilting (removing silt and debris from within the system)

    • We expect to remove a total of approximately 1360 tonnes from the asset
    • we will be desilting from Vincents Avenue, Rockdale and Subway Road, Rockdale
    • there will be changes to local traffic and increased truck movements for deliveries and the disposal of silt and debris.

    Tunnel Repairs

    • cleaning and surface preparation
    • removal and replacement of internal structures (ladders, step irons within the wastewater tunnel
    • core hole drilling and final inspection.

    Restoration

    • Once the above work is finished, all sites will be disestablished and impacted areas will be restored. All restoration works will be performed in accordance with Council and Traffic NSW requirements.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work is planned for Sunday or public holidays.

    Click here to read the community newsletter for more detailed information.

  • Rockdale 2216

    Share Rockdale 2216 on Facebook Share Rockdale 2216 on Twitter Share Rockdale 2216 on Linkedin Email Rockdale 2216 link

    Northern Georges River Submain - Wastewater Upgrade

    Project timing: May 2024 to August 2025

    We’re upgrading 3 km section of a large wastewater main knows as the Northern Georges River Submain. This system services the community from Fairfield to Arncliffe. Our work will increase the capacity within the tunnel, improving its function and reliability of your wastewater service.

    Most of our work is underground, however we will have four major sites set up above ground for access into the wastewater system and desilting activities.

    Work involves:

    Site establishment and traffic management

    • four major sites and four minor sites will be set up in suburbs Arncliffe, Rockdale and Kogarah

    Desilting (removing silt and debris from within the system)

    • We expect to remove a total of approximately 1360 tonnes from the asset
    • we will be desilting from Vincents Avenue, Rockdale and Subway Road, Rockdale
    • there will be changes to local traffic and increased truck movements for deliveries and the disposal of silt and debris.

    Tunnel Repairs

    • cleaning and surface preparation
    • removal and replacement of internal structures (ladders, step irons within the wastewater tunnel
    • core hole drilling and final inspection.

    Restoration

    • Once the above work is finished, all sites will be disestablished and impacted areas will be restored. All restoration works will be performed in accordance with Council and Traffic NSW requirements.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work is planned for Sunday or public holidays.

    Click here to read the community newsletter for more detailed information.

  • Mascot 2020

    Share Mascot 2020 on Facebook Share Mascot 2020 on Twitter Share Mascot 2020 on Linkedin Email Mascot 2020 link

    Mascot Wastewater Pumping Station Mechanical & Electrical Upgrade

    6 Coleman Street, Mascot

    We are upgrading the Mascot wastewater pumping station.

    Construction activities will include:

    • replacing internal infrastructure such as pumps, ventilation system, valves and pipes

    • improving access to equipment within the pumping station

    • upgrading the existing above ground infrastructure

    • restoring areas impacted by our work.

    Some of this work needs to be done at night due to wastewater flow levels. We know this is not ideal, but we’ll do everything we can to keep noise to a minimum.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work planned on Public Holidays.

    Night work hours: 7 pm to 5 am

    Start: June 2021 Finish: This work is currently on hold.




  • Kogarah 2217

    Share Kogarah 2217 on Facebook Share Kogarah 2217 on Twitter Share Kogarah 2217 on Linkedin Email Kogarah 2217 link

    Northern Georges River Submain - Wastewater Upgrade

    Project timing: May 2024 to August 2025

    We’re upgrading 3 km section of a large wastewater main knows as the Northern Georges River Submain. This system services the community from Fairfield to Arncliffe. Our work will increase the capacity within the tunnel, improving its function and reliability of your wastewater service.

    Most of our work is underground, however we will have four major sites set up above ground for access into the wastewater system and desilting activities.

    Work involves:

    Site establishment and traffic management

    • four major sites and four minor sites will be set up in suburbs Arncliffe, Rockdale and Kogarah
    • The site in Kogarah is located on Gladstone Avenue - you will notice a temporary change to the pedestrian walkway around the compound area - for your safety please follow the traffic and pedestrian signs.

    Desilting (removing silt and debris from within the system)

    • We expect to remove a total of approximately 1360 tonnes from the asset
    • we will be desilting from Vincents Avenue, Rockdale and Subway Road, Rockdale
    • there will be changes to local traffic and increased truck movements for deliveries and the disposal of silt and debris.

    Tunnel Repairs

    • cleaning and surface preparation
    • removal and replacement of internal structures (ladders, step irons within the wastewater tunnel
    • core hole drilling and final inspection.

    Restoration

    • Once the above work is finished, all sites will be disestablished and impacted areas will be restored. All restoration works will be performed in accordance with Council and Traffic NSW requirements.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work is planned for Sunday or public holidays.

    Click here to read the community newsletter for more detailed information.