Lakemba 2195

Critical Watermain Renewal

Lakemba Street, Lakemba.

We’re replacing a section of the water main in your street.

Work involves:

  • service location
  • topographical survey
  • restoration and pack up.

Once Stage 1 is complete, we will return to site within 10 to 12 days to complete Stage 2

  • non-destructive excavation
  • waste sampling and classification
  • restoration and pack up.

Stage 1 Investigations work - Start: 22 May 2022 Finish: Late-June 2023

Stage 2 Construction will be completed in 2024. You'll be notified before we start this work.