Start of investigations
Thank you to everyone who provided feedback in our night work schedule survey. We have carefully considered all feedback to finalise our night work schedule. We’ll work up to four consecutive nights a week from Monday night to Friday morning.
Our investigations will take about three weeks to complete following this schedule, weather and ground conditions permitting. Our work will start on Wednesday 30 November and is expected to finish by Friday 23 December 2022.
This work will be done at night to reduce the impact on daytime traffic flows and local businesses. Our night work hours are 8 pm to 5 am, Monday nights to Friday mornings. We won’t work Friday, Saturday or Sunday nights.
Once we’ve finished our investigations, we will return later to start construction of the new water main. We’ll write to you again to let you know before we start.