Green Square Stormwater Drain Project - Maddox Street to Alexandra Canal

Share on Facebook Share on Twitter Share on Linkedin Email this link
Our work on the northern side of Huntley Street Bridge is nearly finished. Huntley Street returned to two-way traffic in November 2017 and apart from some planned night time road closures, this will not change until we finish our work. We'll keep the local community informed of all our upcoming night work.

The project has suffered unfortunate delays, but we're now progressing the relocation of telecommunications, water, gas and electricity services on the southern side of Huntley Street. We appreciate the community's support during this important work.

Huntley Street

Huntley Street returned to two-way traffic in November 2017 and albeit for some planned night time road closures, this will not change until we finish our work.

We’ve largely completed the relocation of telecommunications, water, gas and electricity services and are now working on the new bridge deck on the southern side of Huntley Street. This will allow us to complete the new bridge to replace the existing bridge that has almost reached its lifespan.

We expect all our work to be finished in September 2019.


Sheas Creek

We've widened the Sheas Creek stormwater channel between Maddox Street

Huntley Street

Huntley Street returned to two-way traffic in November 2017 and albeit for some planned night time road closures, this will not change until we finish our work.

We’ve largely completed the relocation of telecommunications, water, gas and electricity services and are now working on the new bridge deck on the southern side of Huntley Street. This will allow us to complete the new bridge to replace the existing bridge that has almost reached its lifespan.

We expect all our work to be finished in September 2019.


Sheas Creek

We've widened the Sheas Creek stormwater channel between Maddox Street and Alexandra Canal.

This work involved:

  • excavating along the existing open channel along Sheas Creek, between Maddox Street and Alexandra Canal
  • building a brand new, shared pedestrian and cycle path. This path will connect Maddox Street to Alexandra Canal
  • diverting and relocating existing utility services in Huntley Street so we could widen and replace the bridge
  • removing the culverts under the bridge to accommodate flood waters ( see picture)
  • upgrading the bridge deck in sections.



  • Business and pedestrian access

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    by claudia.clavijo, about 4 years ago

    During the work, we'll maintain access to Huntley Street for pedestrians, but there'll be some diversions in place to guide people around our work areas.

    We'll maintain access to businesses in Huntley Street for owners, staff, customers and deliveries. Some driveways near the bridge will be temporarily closed while we do the bridge work but we're working closely with those affected to make sure they have alternative access.

    During the work, we'll maintain access to Huntley Street for pedestrians, but there'll be some diversions in place to guide people around our work areas.

    We'll maintain access to businesses in Huntley Street for owners, staff, customers and deliveries. Some driveways near the bridge will be temporarily closed while we do the bridge work but we're working closely with those affected to make sure they have alternative access.

  • More information

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    by claudia.clavijo, about 4 years ago

    If you would like more informaiton about what to expect during the construction of the stormwater drain in and around Huntley Street you can download a copy of our community update (insert hyperlink).

    For more information about the project in general, or to give us your feedback, please call 1300 883 648 or email stormwater@dgalliance.com.au.

    We appreciate your cooperation and patience during this important work.



    If you would like more informaiton about what to expect during the construction of the stormwater drain in and around Huntley Street you can download a copy of our community update (insert hyperlink).

    For more information about the project in general, or to give us your feedback, please call 1300 883 648 or email stormwater@dgalliance.com.au.

    We appreciate your cooperation and patience during this important work.