Upcoming extended work hours for wastewater pipe installation between Pratten Street and Exeter Road, Kemps Creek

Our delivery partner, Quickway, is currently installing two wastewater pipes between Pratten Street and Exeter Road, Kemps Creek, which commenced on Monday 17 February 2025.

To install these new wastewater pipes, Quickway will be 'micro-tunnelling' underground, using two Tunnel Boring Machines (TBMs) to drill through soil and rock along the project alignment to enable the installation.

To minimise impacts to our community by reducing the overall time needed to complete this important work, we consulted with the community in late 2024 to extend our work hours to include working on Saturdays from 8 am to 5 pm. Following the close of consultation, and submission of the extended work hours proposal to The Environmental Protection Authority, our extended work hours have been approved.

Starting Monday 17 February 2025, our Monday to Friday work hours will be 7 am to 6 pm and Saturdays 8 am to 5 pm, until late March 2025, weather permitting. There will be no work on Sundays and public holidays.

If you have any questions, please email our community engagement team at kempscreekwastewater@sydneywater.com.au or call 1300 989 496.

We appreciate your understanding and patience during this essential work.

Share Upcoming extended work hours for wastewater pipe installation between Pratten Street and Exeter Road, Kemps Creek on Facebook Share Upcoming extended work hours for wastewater pipe installation between Pratten Street and Exeter Road, Kemps Creek on Twitter Share Upcoming extended work hours for wastewater pipe installation between Pratten Street and Exeter Road, Kemps Creek on Linkedin Email Upcoming extended work hours for wastewater pipe installation between Pratten Street and Exeter Road, Kemps Creek link