Upcoming night work on Elizabeth Drive

To install the dual pressure mains, we will micro-tunnel from Cross Street across Elizabeth Drive. Before we do this, we need to install settlement monitoring markers along the centre line of the micro-tunnel boring location, and 5 metres either side from the centre line of Elizabeth Drive. These settlement monitoring markers will be in place to ensure there is no movement in the road while the micro tunnelling is completed.

We will be installing the settlement monitoring markers at night on Friday 16 August 2024 from 9 pm, weather permitting. This work should take approximately 3 hours to complete.

Due to Road Occupancy Licence restrictions, we are unable to complete our works during standard working hours.

What will this work involve?

Our team will be using handheld drills to install the settlement markers directly into the ground

What noise impacts will the work produce?

The works will include the use of hand-held drills and minimal light vehicle movements around the site. The predicted noise impact is from quiet to moderate which can be compared to the noise of passing traffic.

What do you need to know?

We know our work can be disruptive, so we’ll make every effort to reduce any impact this work may have on you.

Traffic management will be in place on Elizabeth Drive. There will be workers on foot installing the markers, please be mindful if traveling in this area.