Improving the wastewater system near Barney Street

We’ve been working to improve the wastewater system off Barney Street, Kiama, to help reduce wastewater overflows on private properties during wet weather events.

When we started in February 2022, we honestly thought our project would be finished by now and the new Emergency Relief Structure (ERS) that we’ve been building would be operational.

Unfortunately this project has not gone to plan and we’ve had a number of setbacks. The latest being deficiencies found in the Epoxy coating applied to the new ERS. Repairs will need to be made to this coating to ensure it functions as intended into the future.

The remaining work on site includes:

  • remediation of the Epoxy coating inside the ERS
  • test and commission the new ERS
  • installation of safety screens beneath the concrete lids.

We’ll be starting to do these activities from Monday 12 February and will try to finish as soon as we can. Due to the nature of the remaining work, it will happen intermittently, and residents will notice some temporary ATF fencing around the ERS from time to time. We’ll aim to leave this in place for as short a time as possible.

Access to the beach, shared pathways, car park, picnic tables and showers will not be affected.

We sincerely appreciate the cooperation from the community that we’ve continued to receive and we apologise that this project has taken longer than originally expected.

Epoxy is a protective paint used on concrete surfaces in wastewater systems for water proofing and to protection against corrosion.



Barney Street car park and reserve restored December 2022




Timeline photos

Overview of the ERS excavation site
May 2022

Existing concrete encased clay wastewater pipe that needs to be replaced
May 2022

24 hour bypass pump arrangement ready for use in July 2022

Installing shoring (reinforcement) using a crane at the new ERS site in June 2022

Cutting into the existing live concrete encased wastewater main where the new ERS will be constructed in July 2022

New wastewater pipe that was installed to replace the old clay concrete encased pipe. The new ERS will be build around this pipe.
August 2022

Progressive concrete pours to construct the new ERS up to existing ground levels.
August 2022

Preparation of next concrete pour as new ERS is constructed.
September 2022

Continued backfilling of excavation site as new ERS is constructed.
September 2022

Instillation of new culvert.
October 2022

Excavation backfill nearing completion.
October 2022

Gatic lids partially installed, waiting to be filled in with concrete to provide finished surface
November 2022

Restoration of garden bed at entrance to car park
December 2022


Restoration of car park
December 2022


Categories: #BarneyStreet #wastewater #ERS #EmergencyReliefStructure #Kiama #D4C #Delivering4Customers #KendallsBeach, #SydneyWater
Share Improving the wastewater system near Barney Street on Facebook Share Improving the wastewater system near Barney Street on Twitter Share Improving the wastewater system near Barney Street on Linkedin Email Improving the wastewater system near Barney Street link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>