Concrete pour planned for 24 June 2022

There are 10 major concrete pours planned over the next nine months to build the two digesters. We completed one last week and our next pour is planned for Friday 24 June, weather permitting. If we’re not able to complete the pour on Friday, we will defer the work to Monday 27 June.
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility.
This means some of our deliveries will be outside our standard working hours on that day, including:
- during school zone hours (between 8 am and 9:30 am and 2:30 pm and 4 pm)
- between 6 am and 7 am in the morning