Concrete pour planned for 27 October 2022

We've completed four of the 10 concrete pours for the new digesters so far and our next pour is planned for Thursday 27 October, weather permitting.

We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:

  • during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
  • between 6 am and 7 am in the morning.