Concrete pour planned for Thursday 15 December 2022

We've completed seven of the 10 concrete pours for the new digesters so far and our next pour is planned for Thursday 15 December, weather permitting. If we’re not able to complete the pour on Thursday, we will defer the work to Friday 16 December .

We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:

  • during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
  • between 6 am and 7 am in the morning.
Share Concrete pour planned for Thursday 15 December 2022 on Facebook Share Concrete pour planned for Thursday 15 December 2022 on Twitter Share Concrete pour planned for Thursday 15 December 2022 on Linkedin Email Concrete pour planned for Thursday 15 December 2022 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>