Work set to recommence between Quakers Hat Bay and The Spit

The Spit Syphon site was made ready in December 2022 for work to start completing rehabilitation of the 1.3km section of tunnel between Quakers Hat Bay and The Spit.

Crews are using custom made machinery to remove silt and other debris from inside the tunnel. After dewatering at the Quakers Hat Bay site, this material is transported daily in covered skips to a licensed waste facility.

Limited tunnel repairs (pinning of concrete) commenced inside this section of the NSOOS in the second quarter of 2023

A new cover was installed behind the Spit Syphon in late February. The temporary structure stops odours from escaping when tunnel lids in the Syphon are opened

Share Work set to recommence between Quakers Hat Bay and The Spit on Facebook Share Work set to recommence between Quakers Hat Bay and The Spit on Twitter Share Work set to recommence between Quakers Hat Bay and The Spit on Linkedin Email Work set to recommence between Quakers Hat Bay and The Spit link