Malabar Water Resource Recovery Facility Plant - Fencing Project
We are installing new fencing around the Malabar Water Resource Recovery Facility. The new fencing will ensure the security of the facility and a substantial improvement to the aesthetics and amenity of the facility for residents and visitors.
Work has started and is expected to finish by September 2023, weather permitting.
The work will include:
- revegetation around the Facility with native plants, information about the plants, and their traditional uses
- construction of a concrete pathway, seating, and stairs leading into the National Park at the end of Fishermen’s Road
- construction of an Indigenous yarning circle, Facility signage, and drinking water filling station located at the Fisherman’s Road entry to the Facility
Artiste Impression of the Yarning Circle
- site set up, including amenities and safety measures at the Franklin Street entry area to the Facility
- clearing of vegetation along the perimeter of the Facility
- construction of concrete footings and installation of palisade-type fencing to the entire perimeter of the Facility
- restoration and revegetation of disturbed areas during the construction phases of the works

Share Malabar Water Resource Recovery Facility Plant - Fencing Project on Facebook
Share Malabar Water Resource Recovery Facility Plant - Fencing Project on Twitter
Share Malabar Water Resource Recovery Facility Plant - Fencing Project on Linkedin
Email Malabar Water Resource Recovery Facility Plant - Fencing Project link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends