Night Utility Investigation Work

Our delivery partner, John Holland, will be completing investigation work by potholing to confirm the location of underground utilities along the route of the brine pipeline in Kemps Creek, Cecil Hills, Green Valley, Bonnyrigg, Bonnyrigg Heights, Cabramatta West and Canley Vale.

We will work from Monday 3 July until Friday 14 July 2023, weather permitting. Our working hours will be from 8 pm to 6 am Monday to Friday. We are completing this work at night to maintain safety for road users and workers and to keep people moving during peak travelling times.

We will use concrete saw cutters, excavators and vacuum trucks to form a pothole and confirm the location and depth of underground utilities. If required, jack hammers will also be used. We will also use lighting towers to light our work area. We will then fill and compact the pothole and restore the road or footpath surface.

This work will be noisy however we will coordinate our work so that residents do not experience noise for more than two consecutive nights, or more than three nights in total in one week.

We will be potholing in the following locations:

  • Cross Street at the intersection of Devonshire Road, Kemps Creek
  • Western Road between Elizabeth Drive and Overett Avenue, Kemps Creek
  • Feodore Drive near Spencer Road, Cecil Hills
  • North Liverpool Road between the Liverpool-Parramatta Transitway and Whitford Road and at Currawong Street, Green Valley
  • North Liverpool Road at the intersection of Montgomery Road, Bonnyrigg
  • Montgomery Road near Kincumber Road and Brown Road, Bonnyrigg
  • Montgomery Road near Holdin Street, Bonnyrigg
  • North Liverpool Road at Wilson Road, Bonnyrigg Heights
  • Cabramatta Road West near Tarlington Parade, Cabramatta West
  • Monash Place, Cabramatta West
  • Hebblewhite Place, Cabramatta West
  • Chancery Street between Vale Street and Landsdowne Road, Canley Vale
  • Beckenham Street, between Bromley Street and Willowbank Crescent, Canley Vale

There will be temporary traffic changes to ensure the work zone is safe. Partial lane closures and speed reductions may be in place at times and there may be some loss of on-street parking while the work is being completed. Please keep to speed limits and follow signs and the direction of traffic controllers.