December 2019

Concept design finalised

June 2020

REF on display

December 2020

Decision Report published

September 2021

Delivery Partner appointed

November → December 2021

Site investigations

December 2021

Parsley Bay amenities concept design display

February → September 2022

Detailed design development and consultation

November 2022

Final design and IFC

February 2023

Expected start of construction

December 2024 → February 2025

Expected project completion