Update: MBR concrete pour dates

We will temporarily extend our work hours for to allow our delivery partner Downer|BMD to complete these concrete works for Membrane Bioreactors (MBR).

The construction of the MBR slabs will be poured over five large pours, each pour requiring to be completed in a single shift. The concrete pours will be completed during the earlier hours however with cooler temperatures it will take longer for the concrete to dry and finishing works to be completed.

Our works hours for the concrete pour will be from 4am to midnight.

The concrete pours will be done on the following dates:

  • Monday 17 October 2022
  • Wednesday 26 October 2022

Our standard working hours will not change. We will continue to work Monday to Friday from 7am to 6pm and Saturdays from 7am to 5pm.

We will not work on Sundays or Public Holidays