Kemps Creek - Traffic changes during nightworks at Cross St/ Devonshire St

A section of the 4.5 km of new water main in Kemps Creek will need to be installed at the intersection of Cross Street and Devonshire Road.

We will do this work at night to minimise the impact to road users at this busy intersection.

Night work will take place for a period of up to 10 nights between Sunday 14 March and Thursday 8 April from 8 pm to 5 am.

Traffic changes

The intersection of Devonshire Road and Cross Street will be closed while we do this work. A detour will be in place via Elizabeth Drive, Western Road and Exeter Road. Traffic management will be in place to safely direct vehicles and pedestrians around the work site. Local access will be maintained, however there may be some delays. Please see map for more details.


Following this, installation of the pipeline will continue west along Cross Street in front of Kemps Creek Public School and Christadelphian Heritage College. We will complete this work during the school holidays to minimise the impact to school traffic.



Share Kemps Creek - Traffic changes during nightworks at Cross St/ Devonshire St on Facebook Share Kemps Creek - Traffic changes during nightworks at Cross St/ Devonshire St on Twitter Share Kemps Creek - Traffic changes during nightworks at Cross St/ Devonshire St on Linkedin Email Kemps Creek - Traffic changes during nightworks at Cross St/ Devonshire St link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>