October 2020 → April 2021

Early Works for Oran Park Reservoir construction

January → February 2021

Cecil Hills - construction of pipeline connecting Liverpool Reservoir to Cecil Park

November 2020 → December 2021

Construction of pumping station and pipe works at Liverpool reservoir

December 2020 → July 2022

Construction of Oran Park Reservoir

February 2021 → May 2022

Construction of Harrington Park Pumping Station

January 2021 → May 2022

Construction of pipeline from Moyengully Reserve (Mount Annan/ Narellan) to Sugarloaf pumping station (Menangle Park)

February → November 2021

Construction of pipeline from Cecil Park Reservoir to Sydney International Shooting Center (through Western Sydney Parklands)

January → November 2021

Construction of pipeline from Cecil Hills (Anjou Circuit) to Cecil Park Reservoir (through Western Sydney Parklands)

April → November 2021

Upgrade of Cecil Park Reservoir (in Western Sydney Parklands)

November 2021 → March 2022

Kemps Creek - Construction of pipeline from Range Rd (Cecil Park) to Western Rd (Kemps Creek)