November 2020 → April 2022

Construction of pumping station and pipe works at Liverpool reservoir

October 2020 → August 2022

Construction of Oran Park Reservoir

July 2021 → August 2022

Construction of Harrington Park Pumping Station

May 2021 → May 2022

Construction of pipeline from Moyengully Reserve (Mount Annan/ Narellan) to Sugarloaf pumping station (Menangle Park)

February → November 2021

Construction of pipeline from Cecil Park Reservoir to Sydney International Shooting Center (through Western Sydney Parklands)

January → November 2021

Construction of pipeline from Cecil Hills (Anjou Circuit) to Cecil Park Reservoir (through Western Sydney Parklands)