07 November 2022

Site establishment

First we need to set up our compound area within Whiteoak Reserve. 

Work will involve:

  • setting up ATF fencing within Whiteoak Reserve to surround and secure the work area
  • using a crane to set up our site sheds and worker amenities
  • laying down road base along the truck route 
  • installing time lapse cameras to record our progress from start to finish (cameras will not face into any surrounding properties)

The landscaping and restoration plan is still being developed in consultation with Bayside Council. We will post the plan on this page once it has been finalised.

20 September 2024

Expected project completion

We expect to complete the work in late 2024. As you may be aware, wet weather can impact our ability to work, especially within a creek. 


We will keep the community updated on our timeline. We will also be working on Saturdays to get the work done as quickly and safely as we can.

29 October 2022

Community Information Day

Join us for a free sausage sizzle, fun activities for the
kids and to learn more about our work at Muddy
Creek.
The project team from Sydney Water and our partner
D4C will be on hand to discuss this project and
answer your questions.

Where: Whiteoak Reserve, entry near Francis Street

Time: 9:30 am to 11:30 am

RSVP: deliveringforcustomers@sydneywater.com.au


23 December 2022 → 09 January 2023

Holiday shutdown period

  We are going to shutdown the worksite for two weeks over the holiday period.

We return to site on Monday 8 January, 2024.

For urgent matters while we're away, please call 13 20 90.

09 September 2023

Community Drop In!

Come and see our progress so far. 

We'll meet at St george Netball Courts and take a stroll down to the pedestrian bridge to look at what we've completed so far.

Come and meet the Project Team and have a free coffee on us!

06 November 2023

Removal and replacement of the pedestrian bridge

We're replacing the pedestrian bridge with a brand new one! This  will take a month or so to complete. The bridge will be back and open for use in the new year. 

22 December 2023

Holiday Shutdown (2 weeks)

We'll stop work and securely shutdown the site while we take a break in the summer holidays.
We'll start back again on Monday 8 January 2024.