Site establishment at Dover Heights
In late December 2023 we appointed Abergeldie Complex Infrastructure (ACI) to deliver the Refresh Vaucluse and Diamond Bay project.
Sydney Water’s property on the corner of Portland Street and Lancaster Road will be the site compound for this work. We will start site compound establishment work from late February 2024.
What you need to know
You will notice the following work activities:
- Minor vegetation clearing within the compound area
- Widening gates, installing fencing and signage
- Delivery of equipment, temporary site sheds and facilities
- Establishing parking, laydown, stockpile, plant and equipment storage areas
We will ensure our contractors are parking on site. Access to properties and the bus stop on Portland Street will be maintained.
We’ll make every effort to reduce any impact our work may have on you.
Work hours
Our work hours will be from 7 am to 6 pm Monday to Friday and from 8 am to 1 pm on Saturdays. The site compound may be in use after these hours with light vehicles only entering and exiting during that time.