We're renewing the wastewater main on council land behind Edgar Street. Work started in January 2024 and is expected to finish around mid-2024, weather and ground conditions permitting.

Work will involve (see below map)

  • setting up a temporary site compound with amenities for workers
  • complete home plans with directly impacted private property owners
  • clear the construction corridor and access route of existing trees as per Section 46 of the Sydney Water Act 1994
  • replace the wastewater main at the back of Edgar Street on council land
  • test and commission the wastewater main then reconnect private properties
  • restore the construction and access corridor as close as practicable to preconstruction conditions and demobilise from site.