Northwest Growth Area Stage 1 - New services in Bidwill, Marsden Park and Riverstone

Share Northwest Growth Area Stage 1 - New services in Bidwill, Marsden Park and Riverstone on Facebook Share Northwest Growth Area Stage 1 - New services in Bidwill, Marsden Park and Riverstone on Twitter Share Northwest Growth Area Stage 1 - New services in Bidwill, Marsden Park and Riverstone on Linkedin Email Northwest Growth Area Stage 1 - New services in Bidwill, Marsden Park and Riverstone link

To meet the needs of growing communities in Northwest Sydney, we’re planning to install new drinking water and wastewater services in Marsden Park, Bidwill, Riverstone and surrounding suburbs.

This project forms part of Sydney Water's wider plans to deliver new services across Northwest Sydney to accommodate for about 33,000 new homes over the next 10 years.

This project will be delivered in various stages, with Stage 1 commencing construction from July 2023 and continuing through to late 2025.

Further details about Stage 1 works, can be found in our Project Newsletters section on the right, and the Newsfeed section below.

For more information about the wider Northwest growth area precinct as well as other growth projects across Sydney, you can visit the Servicing growth and release areas page on our website and view our Growth Servicing Plan.

We will provide more information regarding other stages of this project as we progress.

To meet the needs of growing communities in Northwest Sydney, we’re planning to install new drinking water and wastewater services in Marsden Park, Bidwill, Riverstone and surrounding suburbs.

This project forms part of Sydney Water's wider plans to deliver new services across Northwest Sydney to accommodate for about 33,000 new homes over the next 10 years.

This project will be delivered in various stages, with Stage 1 commencing construction from July 2023 and continuing through to late 2025.

Further details about Stage 1 works, can be found in our Project Newsletters section on the right, and the Newsfeed section below.

For more information about the wider Northwest growth area precinct as well as other growth projects across Sydney, you can visit the Servicing growth and release areas page on our website and view our Growth Servicing Plan.

We will provide more information regarding other stages of this project as we progress.

  • Works on South Street Marsden Park have been completed

    Share Works on South Street Marsden Park have been completed on Facebook Share Works on South Street Marsden Park have been completed on Twitter Share Works on South Street Marsden Park have been completed on Linkedin Email Works on South Street Marsden Park have been completed link

    We have now finished construction work to install a new drinking water pipe on South Street, near Glengarrie Road, Marsden Park.

    We thank you for your patience and cooperation during this work.

  • Results of Luxford Road night works survey - Thank you for your feedback

    Share Results of Luxford Road night works survey - Thank you for your feedback on Facebook Share Results of Luxford Road night works survey - Thank you for your feedback on Twitter Share Results of Luxford Road night works survey - Thank you for your feedback on Linkedin Email Results of Luxford Road night works survey - Thank you for your feedback link

    Thank you for your feedback!

    We asked residents in Bidwill for their feedback regarding our night works schedule for works starting in late July.

    Survey Results

    The survey indicated that the majority of residents (57%) would prefer us to work four nights a week for nine months.

    Please see a summary of the survey results below.

    Based on your feedback, we will be proceeding with our preferred option of four nights per week.

    We thank everyone who took the time to complete the survey.

    We will be in touch prior to work starting and will keep you updated as work progresses.

  • Night works on Luxford Road starting from 20 November 2023

    Share Night works on Luxford Road starting from 20 November 2023 on Facebook Share Night works on Luxford Road starting from 20 November 2023 on Twitter Share Night works on Luxford Road starting from 20 November 2023 on Linkedin Email Night works on Luxford Road starting from 20 November 2023 link
    supporting image

    We're installing a new drinking water pipe in Bidwill.

    We have started early investigation works on Luxford Road and will commence construction in late November 2023. We expect this work to take about nine months to complete.

    Work taking place on Luxford Road will need to take place a night to avoid impacts to traffic flow during the day.

    If you live in the area and would like to receive regular email updates, please click here to provide us with your details.

    For more information, please see our project newsletter.

  • Work on South Street, near Glengarrie Road, Marsden Park to start from 3 July 2023

    Share Work on South Street, near Glengarrie Road, Marsden Park to start from 3 July 2023 on Facebook Share Work on South Street, near Glengarrie Road, Marsden Park to start from 3 July 2023 on Twitter Share Work on South Street, near Glengarrie Road, Marsden Park to start from 3 July 2023 on Linkedin Email Work on South Street, near Glengarrie Road, Marsden Park to start from 3 July 2023 link
    supporting image

    We're installing a new section of drinking water pipe on South Street, Marsden Park.

    We're starting from 3 July 2023 and expect this work to take about six weeks to complete.

    This work till take place during normal construction hours between 7am to 6pm Monday to Friday.

    For more information please see our project newsletter.

Page last updated: 26 Mar 2024, 06:30 PM