North Head Biosolids Upgrade Project
The North Head Water Resource Recovery Facility (previously known as the North Head Wastewater Treatment Plant) serves over one million Sydneysiders: from Seven Hills in the west, Yagoona in the south, and Ku-ring-gai and Collaroy in the north.
We’re building two new digesters and upgrading equipment to improve how we process biosolids at our North Head WRRF.
The biosolids project will:
![]() | Reduce odour Improving the quality of the biosolids will make them less smelly. This means less odour as our trucks transport biosolids from North Head to farms in regional NSW. | ![]() | Contribute to a circular economy Recovering biosolids for reuse in agriculture helps reduce waste to landfill and contribute to a circular economy. |
![]() | Produce better quality biosolids Biosolids are used in agriculture to fertilise soil. Better quality biosolids will ensure we can continue to reuse 100% of the biosolids created. | ![]() | Increase processing capacity Two new digesters will increase sludge processing from 40 to 70 tonnes per day by 2043. |
![]() | Improve reliability In the long run, the new digesters and upgrades to sludge tanks will ensure the ongoing reliability of the facility | ||
The North Head Water Resource Recovery Facility (previously known as the North Head Wastewater Treatment Plant) serves over one million Sydneysiders: from Seven Hills in the west, Yagoona in the south, and Ku-ring-gai and Collaroy in the north.
We’re building two new digesters and upgrading equipment to improve how we process biosolids at our North Head WRRF.
The biosolids project will:
![]() | Reduce odour Improving the quality of the biosolids will make them less smelly. This means less odour as our trucks transport biosolids from North Head to farms in regional NSW. | ![]() | Contribute to a circular economy Recovering biosolids for reuse in agriculture helps reduce waste to landfill and contribute to a circular economy. |
![]() | Produce better quality biosolids Biosolids are used in agriculture to fertilise soil. Better quality biosolids will ensure we can continue to reuse 100% of the biosolids created. | ![]() | Increase processing capacity Two new digesters will increase sludge processing from 40 to 70 tonnes per day by 2043. |
![]() | Improve reliability In the long run, the new digesters and upgrades to sludge tanks will ensure the ongoing reliability of the facility | ||
-
Crane removal out-of-hours
Share Crane removal out-of-hours on Facebook Share Crane removal out-of-hours on Twitter Share Crane removal out-of-hours on Linkedin Email Crane removal out-of-hours linkNow that the two new digesters are finished, we need to remove the tower crane from our site.
We'll need to dismantle the crane and remove it using five semi-trailer movements. This means there will some heavy vehicle movements to and from the facility between 6 am and 5 pm on Saturday 21 October. If we aren't able to remove the crane on Saturday 21 October, we'll defer the work to Saturday 28 October..
We’ll make every effort to minimise impacts on our neighbours during this delivery and avoid unnecessary loud noises, however the movement of the trucks for this brief period will be noisy.
-
Our two new digesters are now complete!
Share Our two new digesters are now complete! on Facebook Share Our two new digesters are now complete! on Twitter Share Our two new digesters are now complete! on Linkedin Email Our two new digesters are now complete! linkWe recently completed an important milestone for our Biosolids upgrade project – construction of our two new digesters is now finished!
Standing over 14 metres high, our work to build the two new digesters involved pouring over 1,300 cubic metres of concrete in ten stages. This was done over eight months between August 2022 and March 2023.
The two new digesters will increase the processing capacity of the facility from 40 tonnes to 70 tonnes of sludge per day by 2043 and contribute to reusing 100% of biosolids created as fertiliser on farms in NSW.
Our next steps are to install new fittings and equipment to support the two new digesters as well as completing some tests and checks to get them ready for use.
The aerial picture shows our two new digesters recently installed.
-
Concrete pour planned for Tuesday 14 March 2023
Share Concrete pour planned for Tuesday 14 March 2023 on Facebook Share Concrete pour planned for Tuesday 14 March 2023 on Twitter Share Concrete pour planned for Tuesday 14 March 2023 on Linkedin Email Concrete pour planned for Tuesday 14 March 2023 linkWe've completed nine of the 10 concrete pours for the new digesters so far and our next pour is planned for Tuesday 14 March, weather permitting. If we’re not able to complete the pour on Tuesday, we will defer the work to Wednesday 15 March
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
-
Concrete pour planned for Wednesday 22 February 2023
Share Concrete pour planned for Wednesday 22 February 2023 on Facebook Share Concrete pour planned for Wednesday 22 February 2023 on Twitter Share Concrete pour planned for Wednesday 22 February 2023 on Linkedin Email Concrete pour planned for Wednesday 22 February 2023 linkWe've completed eight of the 10 concrete pours for the new digesters so far. We weren’t able to complete the concrete pour planned for Tuesday 7 February or Thursday 9 February due to wet weather, so we’ve rescheduled this pour for Wednesday 22 February, weather permitting. If we’re not able to complete the pour on Wednesday, we will defer the work to Thursday 23 February.
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
-
Concrete pour planned for Tuesday 7 February 2023
Share Concrete pour planned for Tuesday 7 February 2023 on Facebook Share Concrete pour planned for Tuesday 7 February 2023 on Twitter Share Concrete pour planned for Tuesday 7 February 2023 on Linkedin Email Concrete pour planned for Tuesday 7 February 2023 linkWe've completed eight of the 10 concrete pours for the new digesters so far and our next pour is planned for Tuesday 7 February, weather permitting. If we’re not able to complete the pour on Tuesday, we will defer the work to Thursday 9 February.
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
-
Concrete pour planned for Thursday 15 December 2022
Share Concrete pour planned for Thursday 15 December 2022 on Facebook Share Concrete pour planned for Thursday 15 December 2022 on Twitter Share Concrete pour planned for Thursday 15 December 2022 on Linkedin Email Concrete pour planned for Thursday 15 December 2022 linkWe've completed seven of the 10 concrete pours for the new digesters so far and our next pour is planned for Thursday 15 December, weather permitting. If we’re not able to complete the pour on Thursday, we will defer the work to Friday 16 December .
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
-
Concrete pour planned for Wednesday 7 December 2022
Share Concrete pour planned for Wednesday 7 December 2022 on Facebook Share Concrete pour planned for Wednesday 7 December 2022 on Twitter Share Concrete pour planned for Wednesday 7 December 2022 on Linkedin Email Concrete pour planned for Wednesday 7 December 2022 linkWe've completed six of the 10 concrete pours for the new digesters so far and our next pour is planned for Wednesday 7 December 2022, weather permitting. If we’re not able to complete the pour on Wednesday, we will defer the work to Thursday 8 December 2022.
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
-
Concrete pour planned for 9 November 2022
Share Concrete pour planned for 9 November 2022 on Facebook Share Concrete pour planned for 9 November 2022 on Twitter Share Concrete pour planned for 9 November 2022 on Linkedin Email Concrete pour planned for 9 November 2022 linkWe've completed five of the 10 concrete pours for the new digesters so far and our next pour is planned for Wednesday 9 November, weather permitting. If we’re not able to complete the pour on Wednesday, we will defer the work to Thursday 10 November.
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
-
Concrete pour planned for 27 October 2022
Share Concrete pour planned for 27 October 2022 on Facebook Share Concrete pour planned for 27 October 2022 on Twitter Share Concrete pour planned for 27 October 2022 on Linkedin Email Concrete pour planned for 27 October 2022 linkWe've completed four of the 10 concrete pours for the new digesters so far and our next pour is planned for Thursday 27 October, weather permitting.
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
-
Concrete pour planned for 20 September 2022
Share Concrete pour planned for 20 September 2022 on Facebook Share Concrete pour planned for 20 September 2022 on Twitter Share Concrete pour planned for 20 September 2022 on Linkedin Email Concrete pour planned for 20 September 2022 linkWe've completed three of the 10 concrete pours for the new digesters so far and our next pour is planned for Tuesday 20 September, weather permitting. If we’re not able to complete the pour on Tuesday, we will defer the work to Wednesday 21 September.
We need regular deliveries of concrete throughout the day, so there will be frequent truck movements to and from the facility:
- during school zone hours (between 8 am and 9.30 am and 2.30 pm and 4 pm)
- between 6 am and 7 am in the morning.
Newsletters
-
November 2021 - North Head Biosolids community newsletter.pdf (592 KB) (pdf)
-
June 2022 - North Head Biosolids community newsletter.pdf (567 KB) (pdf)
-
November 2022 - North Head Biosolids community newsletter.pdf (761 KB) (pdf)
-
December 2023 - North Head Biosolids Community Newsletter (752 KB) (pdf)
-
October 2024 - North Head Biosolids Community Newsletter (481 KB) (pdf)
The journey so far
![]() | 2018 REF display |
The Review of Environmental Factors (REF) was displayed for community comment. | |
![]() | 2019 Detailed planning |
We prepared in-depth plans and costs for construction. | |
![]() | 2020 Securing funding |
Funding for the delivery of two new digesters and upgrades to biosolids processing equipment was approved. | |
![]() | 2021 finalising designs and preparing for construction |
We've been working behind the scenes with Confluence Water, our delivery partner, to finalise designs and prepare for construction to start in late 2021. | |
![]() | Late 2021 construction starts |
Construction started in late 2021 and is expected to continue to 2024 |
FAQs
- How will construction impact me?
- What are your construction work hours?
- Will you need out of hours truck movements and deliveries?
- Why was the project split into two phases?
- What do Sydney Water's water resource recovery facilities do?
- What are biosolids?
- What are the benefits of biosolids?
- What is circular economy?
- What is Sydney Water's commitment to circular economy?
Related documents
To know more
-
For general enquiries related to the North Head facility, you can contact the North Head Hub
NHPhone 9934 4423 Email northheadhub@sydneywater.com.au -
For enquiries related to the Biosolids upgrade project
NHPhone 1800 943 119 Email confluence@sydneywater.com.au